Skip to main content
  1. Home
  2. Blog
  3. NEM 3.0 Malaysia Explained | Complete Guide to the Former Net Energy Metering Scheme
Skip to main content

Build your solar plan — no payment until you approve

Configure solar
Trexon Energy logo
About
Sign Up
Calculate Savings
Back to Blog
Policy10 min read

NEM 3.0 Malaysia Explained | Complete Guide to the Former Net Energy Metering Scheme

TE
Trexon Energy Team
Policy & Regulatory
1 March 2026
Trexon Energy Team profile photo - Policy & Regulatory
Trexon Energy Team · Policy & Regulatory1 March 2026

Net Energy Metering 3.0 (NEM 3.0) was the framework that governed how Malaysian solar owners were compensated for electricity they generated, before it closed to new applications at the end of June 2025. Unlike its predecessors, NEM 3.0 prioritised self-consumption over grid export — a design that rewarded owners who used solar power directly in their homes or businesses rather than selling it to TNB. Solar ATAP is the current programme, effective from 1 January 2026. This guide explains exactly how NEM 3.0 worked, its application process, and the savings it delivered — useful if you're researching the scheme's history or are still on a legacy NEM contract.

What is Net Energy Metering (NEM)?

Net Energy Metering is a billing arrangement between solar system owners and Tenaga Nasional Berhad (TNB) that allows excess solar electricity to be credited against your TNB bill. Instead of having two separate transactions (you pay TNB for grid power, TNB pays you for exported solar), NEM nets the two against each other on a single bill.

The Three NEM Generations in Malaysia

Programme Period Mechanism Export Rate
NEM 1.0 2016–2019 1-to-1 offset: exported kWh cancels imported kWh at same tariff rate Same as import tariff
NEM 2.0 2019–2023 Displaced Cost approach: export credited at Displaced Cost Rate (lower than import) RM 0.218–0.245/kWh
NEM 3.0 (closed) 2024–June 2025 Self-consumption first: system sized to self-consume 80%+; export credited at Displaced Cost Rate RM 0.218/kWh (fixed)

How NEM 3.0 Works: The Self-Consumption Model

The key philosophical shift in NEM 3.0 was the sizing guideline. SEDA and TNB required that systems be sized to self-consume the majority of their generation — meaning the solar system should be sized to match your consumption, not to maximise export. Solar ATAP, the current programme, follows the same self-consumption-first logic, but goes further by forfeiting unused export credits at the end of each billing period instead of letting them roll forward.

The NEM 3.0 Billing Mechanism Step by Step

  1. Solar generates during daylight hours. Your panels produce DC electricity, converted to AC by the inverter.
  2. Self-consumption happens first. Any electricity your home/business is consuming at that moment is powered by solar — the grid meter does not spin.
  3. Surplus is exported to TNB. When generation exceeds instantaneous consumption (midday, when appliances are off), excess flows to the grid. Your bi-directional meter records this.
  4. At night or on cloudy days, you draw from the grid. Your meter records TNB imports normally.
  5. Monthly bill calculation: TNB imports are charged at your normal tariff. Exports are credited at RM 0.218/kWh. The credit is applied against your bill — if credits exceed your bill, they carry forward (but are not paid out as cash).

The Critical Difference: Why RM 0.218 Matters

The Displaced Cost Rate (RM 0.218/kWh for export) is significantly lower than the tariff you pay TNB for imports (RM 0.435–0.571/kWh for residential Tariff D, depending on block). This asymmetry means every kWh you self-consume is worth 2–2.6x more than a kWh you export. NEM 3.0 was explicitly designed to encourage self-consumption behaviour, and Solar ATAP carries the same logic forward today — with the added consequence that unused export credits are forfeited monthly rather than rolled forward.

Implication: Oversizing your solar system so it exports large amounts is financially inefficient under Solar ATAP. Size to self-consume. Use our solar savings calculator to find the optimal system size for your bill.

NEM 3.0 vs SELCO vs NOVA: Understanding the Full Landscape (Historical)

This is how the landscape was structured while NEM 3.0 was open. Since June 2025, Solar ATAP has taken NEM 3.0's place for residential and SME applicants — SELCO, NOVA, and CGPP are unaffected.

Programme Best For System Size Limit Export Arrangement
NEM 3.0 (closed) Residential and SME wanting bill offset Up to 75% of approved TNB load RM 0.218/kWh credit against bill
SELCO (Large Scale) Large commercial and industrial (1 MW+) 1 MW–500 MW PPA with TNB at negotiated rate
NOVA Industrial with high self-consumption (no export) No formal cap (consent-based) No grid export — 100% self-consume
Corporate Green Power Programme (CGPP) MNCs needing RE Certificates for ESG Open Virtual PPA — no physical solar required

For residential and SME applications below 1 MW, NEM 3.0 was the standard framework before it closed in June 2025 — Solar ATAP is now the standard framework for that segment. NOVA is increasingly popular for factories wanting to maximise self-consumption without the administrative overhead of TNB grid connection applications.

NEM 3.0 Application Process: Step by Step (Historical Reference)

SEDA is no longer accepting new NEM 3.0 applications — this section is kept for reference and for homeowners tracing an existing NEM contract. If you're applying today, you'll go through the equivalent Solar ATAP process instead. The NEM 3.0 process involved both SEDA (Sustainable Energy Development Authority) and TNB, and took 6–12 weeks from submission to approval:

Step 1: Engage a SEDA-Registered Installer (Your Installer Handles Most of This)

Only SEDA-registered solar contractors can submit NEM applications on your behalf. This is a mandatory requirement — non-registered contractors cannot legally connect a solar system to the TNB grid. Trexon Energy is a registered SEDA contractor.

Step 2: Technical Assessment and System Design

Your installer conducts a site survey, designs the system, and prepares the Single Line Diagram (SLD) and other technical documentation required for submission. System size must not exceed 75% of your approved TNB load (or 12 kW for standard residential single-phase, whichever is lower for Tariff A).

Step 3: SEDA Registration (Online)

Your installer submits the NEM application via SEDA's online portal (nem.seda.gov.my). Documents required: TNB bill, property ownership proof, installer registration number, system design documents. SEDA processing: 2–4 weeks for approval letter.

Step 4: TNB Grid Connection Application

With SEDA approval in hand, your installer applies to TNB for grid connection approval (GCA). TNB inspects the proposed connection point, confirms meter compatibility, and issues a Connection Agreement. TNB processing: 3–6 weeks.

Step 5: Installation

Installation typically takes 1–3 days for residential systems. Your installer handles all electrical work to JKE (Electrical Safety) standards.

Step 6: TNB Inspection and Meter Installation

TNB sends a qualified officer to inspect the completed installation against the approved SLD and install the bi-directional (import/export) meter. This appointment takes 1–3 weeks to schedule after installation completion.

Step 7: Commissioning and SEDA Notification

Once TNB confirms the meter is operational, your installer notifies SEDA of commissioning. Your 21-year NEM approval period begins from this date.

Real Savings Calculation: RM 300 Bill to Under RM 50

This is the calculation most homeowners want to see. Here is a worked example for a Klang Valley household on Tariff D (domestic):

Household Profile

  • Monthly TNB bill: RM 300
  • Monthly consumption: approximately 560 kWh
  • Recommended system: 4 kW solar (NEM 3.0 sizing guidance)
  • System cost: approximately RM 16,000

Monthly Energy Flow (Typical Non-Monsoon Month)

  • Solar generation: 460–480 kWh/month (4 kW × ~115 kWh/kW/month)
  • Self-consumed solar: 350–380 kWh (offset against TNB imports at full tariff rate)
  • Exported to grid: 80–130 kWh (credited at RM 0.218/kWh = RM 17–28)
  • Remaining TNB import: 180–210 kWh

Bill Calculation

  • TNB imports charged: 180–210 kWh × avg RM 0.50/kWh = RM 90–105
  • Less export credit: RM 17–28
  • Net bill: RM 62–88
  • Monthly savings: RM 212–238 (71–79% bill reduction)

In haze-affected months (August–October), generation drops by 15–20%, bringing savings to RM 160–190/month. In optimal dry-season months (March–April), savings can reach RM 250+. Annual average: approximately RM 220–230/month in savings, or RM 2,640–2,760 per year.

On a RM 16,000 system with RM 2,700/year average savings, payback period is approximately 5.9 years — with 15+ years of continued savings thereafter. Check our complete solar panel price breakdown for Malaysia 2026 for detailed cost analysis by system size.

Common NEM 3.0 Misconceptions

  • "My unused export credits will be paid out at year-end." No. NEM 3.0 credits roll forward month to month and expire annually — they are never paid out as cash. Understanding the ATAP monthly credit reset in detail helps you size your system correctly and avoid losing credits. This is why sizing correctly to self-consume is critical.
  • "I can install any size system I want." No. NEM 3.0 system size is capped at 75% of your TNB approved load. Exceeding this requires special approval or switching to a different programme (NOVA or SELCO).
  • "My solar panels stop working during a TNB outage." Correct for standard grid-tied systems — this is a mandatory safety requirement (anti-islanding protection). A battery backup system is required if you want power during blackouts.
  • "I need to re-apply if I move house." Correct. NEM approval is property-specific. If you sell your property, the NEM approval and remaining quota transfers to the new owner with the property.

Ready to go solar under Solar ATAP, the current programme? Our team manages the entire SEDA and TNB process on your behalf. Get in touch with Trexon or use our solar savings calculator to estimate your personalised savings before committing.

Frequently Asked Questions

How long did the NEM 3.0 application take in Malaysia?

NEM 3.0 closed to new applications in June 2025, so this timeline is historical — new applicants now go through Solar ATAP instead. From initial application submission to TNB meter installation: 6–12 weeks. SEDA processing was typically 2–4 weeks, TNB grid connection approval 3–6 weeks, and meter installation scheduling 1–3 weeks after installation completion. Your registered installer manages the entire process — you only need to sign documents at key stages.

What was the maximum solar system size under NEM 3.0?

For residential Tariff A customers, the cap was 12 kW (single-phase) or 75% of your approved TNB load, whichever was lower. Commercial Tariff C customers could go up to 75% of approved load with no absolute kW cap. Systems larger than these limits required the NOVA (no-export) or SELCO (large-scale) programme instead. Note that Sarawak operates under SEB (not TNB) — the Sarawak NEM programme has distinct rules with bill credits that never expire, worth reviewing if your property is in East Malaysia.

Can I claim Solar ATAP and the GITA tax incentive at the same time?

Yes. Solar ATAP (like NEM 3.0 before it) is a billing arrangement with TNB, while GITA (Green Investment Tax Allowance) is a separate incentive from the Malaysian Investment Development Authority (MIDA) applicable to companies (Sdn Bhd) investing in solar. Residential homeowners are not eligible for GITA but may be eligible for the individual income tax deduction on solar installation under Budget 2024 announcements. Both incentives can be claimed simultaneously by eligible business entities.

Related Resources

  • Solar Savings Calculator
  • Residential Solar Solutions
  • Solar Package Pricing
  • Solar Financing Options

See your exact savings

Get a personalized solar proposal in 60 seconds — free, no obligation.

Calculate SavingsWhatsApp Us
Tags
#NEM 3.0#Net Energy Metering#TNB Solar#Solar Policy Malaysia#SEDA Malaysia#Solar ATAP#Self-Consumption
Share Article:
TE
Trexon Energy Team
Policy & Regulatory
Solar Energy Expert

Related Articles

Keep reading — more solar insights for Malaysian homeowners

Browse All Articles
Policy

Solar ATAP Changes 2026: Why You Must Right-Size Your System

The shift from NEM 3.0 to Solar ATAP in 2026 means excess energy credits no longer carry forward. Learn why right-sizing your solar system is crucial for ROI.

5 min readRead article
Policy

Solar ATAP Malaysia 2026: Complete Guide — Application, Export Credits & Savings

Everything about Malaysia's Solar ATAP programme 2026. Who qualifies, how to apply via myTNB, required documents, export credit rates, and real savings examples. Updated March 2026.

10 min readRead article
Policy

Solar ATAP Explained Simply 2026: How Export Credits Work in Malaysia

Confused about Solar ATAP? We explain in plain language how export credits work, what the export rate means for your bill, and the golden rule of solar self-consumption.

7 min readRead article
Policy

Solar ATAP vs SELCO 2026: Understanding Malaysia's Solar Schemes

Confused by the acronyms? We explain the difference between Solar ATAP and Self-Consumption (SELCO) and which is right for you.

6 min readRead article
Browse All Articles

Ready to Start
Saving with Solar?

Get a free personalized quote and discover how much you could save with solar energy for your home or business.

Calculate Your SavingsTalk to an Expert
Free 60-Second Quote

Get your solar savings estimate in 60 seconds

Malaysia's most accurate calculator. No phone number required. Save up to 90% on your TNB bill.

Get Instant QuoteChat on WhatsApp
Trexon Energy logo

Malaysia's SEDA-licensed solar partner since 2020. We design, finance, and install residential, commercial, industrial, and off-grid solar systems.

Registered Office

Thither Global (M) Sdn Bhdtrading as Trexon Energy

G-06-28, Level 6, Block G, Sunway Geo Avenue
Jalan Lagoon Selatan, 47500 Subang Jaya
Selangor, Malaysia

SSM: 201301044881 (1074704-D)

SEDA Licence: SEDA-RPVSP-2026/373

Sales & Support

+60 12-770 7249

WhatsApp Business

+6012-770-7249

Email us

energy@trexon.my

Service Coverage

Peninsular Malaysia, Sabah & Sarawak

Solutions

  • Residential Solar
  • Commercial SolarB2B
  • Industrial Solar
  • Factory SolarGITA
  • Off-Grid Systems
  • Battery Storage
  • BESS for BusinessNew
  • SME Solar
  • CRESSNew
  • Industrial Parks
  • C&I Solar Hub
  • Peak Shaving
  • EV Charging
  • Solar Water PumpsAgri
  • Replace Your GensetNew
  • Strata / JMB SolarNew
  • Data Center SolarNew
  • EV Charging-as-a-ServiceZero Capex
  • Singapore Cross-BorderSG
  • Hospital SolarNew
  • School Solar
  • Telco Tower Solar
  • REIT Portfolio

Services

  • Remote TNB Bill AuditFree
  • Solar Monitoring
  • NEM Application
  • GITA Tax FilingCFO
  • Solar Inspection
  • Energy AuditC&I
  • Sustainability ReportingESG
  • Solar InsuranceNew
  • Singapore Consulting
  • O&M Services
  • All Services

Coverage

  • Solar Kuala Lumpur
  • Solar Selangor
  • Solar Petaling Jaya
  • Solar Shah Alam
  • Solar Penang
  • Solar Johor Bahru
  • Solar Ipoh & Perak
  • Solar Melaka
  • Solar Sarawak
  • All 20+ Locations20+

For Business

  • Submit RFP (5 Min)Free
  • Commercial ROI Calculator
  • PPA (Zero Upfront)
  • IPP Projects
  • Utility-Scale (LSS/CGPP)
  • Industries We Serve
  • Storage, Tracker & BIPV Products
  • Developer APIAPI
  • GITA 60% Tax GuideCFO
  • TNB MD Charge Guide
  • Commercial Case Studies

Tools & Resources

  • Solar ConfiguratorFree
  • Bill Analyzer
  • Priority Site VisitRM100 Credit
  • Diesel vs Solar CalcNew
  • Solar Panel Price 2026
  • Solar Buyer Guides
  • Solar Blog
  • Case Studies
  • Solar ATAP (NEM) Guide
  • FAQ

Company

  • About Trexon Energy
  • Why Choose Trexon
  • Our Team
  • CareersHiring
  • InternshipsOpen
  • Press & Media
  • Investors
  • Installer Partners
  • Referral ProgramRM500
  • Contact Sales

Support & Legal

  • Customer Portal
  • Track My Installation
  • 25-Year Panel Warranty
  • Panel Cleaning
  • O&M Services
  • Sitemap
  • Privacy Policy
  • Terms of Service
  • Refund Policy
SEDA
RPVSP licensed
TNB
Solar ATAP ready
Tier-1
Panels & inverters
RM0
Upfront options
25-yr
Panel warranty
SEDA RPVSP Licensed(SEDA-RPVSP-2026/373)
TNB Solar ATAP Certified
SIRIM Certified Products
ISO 9001:2015
MPIA Member

© 2026 Thither Global (M) Sdn Bhd (201301044881). Trading as Trexon Energy. All rights reserved.

PrivacyTermsRefund PolicySitemap|Protected by reCAPTCHA (Privacy & Terms)
MalaysiaMade with ♥ in Subang Jaya