How a Klang Valley hypermarket hub store used Huawei SUN2000 + Trina Vertex S+ to address cold-chain energy costs and satisfy RSPO/ESG supplier audits
tCO₂ offset annually
“Our single biggest cost driver was Maximum Demand charges from the compressor racks starting simultaneously after the weekend deep-clean cycle. That alone was pushing our MD registration 200 kW above our average demand. Trexon's FusionSolar load-shifting configuration addressed that directly. Four months in, our MD charges have dropped by RM 14,000 per month. The sustainability team also used the FusionSolar generation reports to complete our RSPO supplier questionnaire in under an hour — that used to take three weeks.”
A hypermarket is not a large version of a convenience store. It is a cold-chain logistics hub that happens to have a retail front end. The refrigeration and freezer infrastructure required to maintain 1,500–2,000 SKUs of fresh produce, dairy, meat, and frozen goods across 3,000–5,000 m² of chilled display runs continuously, 24 hours a day, 365 days a year. The compressor racks that power this infrastructure are among the most energy-intensive pieces of commercial equipment in the Malaysian grid.
For this particular national hypermarket chain's Klang Valley hub store — a 28,000 m² gross floor area facility handling regional distribution as well as retail — electricity was the second-largest operating cost after labour. The monthly TNB bill was consistently RM 90,000–100,000, with peak months reaching RM 110,000 during the festive pre-stocking periods in January and October. Of that bill, Maximum Demand charges accounted for approximately RM 26,000–32,000 per month — the single largest line item.
Understanding MD charges is essential to understanding why this project achieved a 32% MD reduction: TNB's C1 and C2 medium-voltage tariffs charge per kW of maximum 30-minute average demand registered in any month. For a hypermarket, the highest MD event typically occurs not during peak shopping hours but during the post-deep-clean compressor restart cycle — when all refrigeration units simultaneously ramp back to operating temperature after the weekly Sunday cleaning shutdown. This simultaneous restart can push instantaneous demand 300–400 kW above the facility's typical trading-hours average, registering an MD peak that inflates the entire month's MD charge.
Trexon's survey team spent three days mapping the facility in November 2025. The site presented two distinct rooftop opportunities:
Zone 1 — Warehouse and Loading Bay Roof (3,200 m²): A flat reinforced-concrete structure with clear south-southwest orientation and structural capacity rated at 35 kg/m² live load — suitable for standard ballasted racking. No roof penetrations required. The warehouse roof's unobstructed expanse made it the primary generation zone.
Zone 2 — Main Retail Roof (5,800 m² gross, 2,100 m² usable): The retail roof is partially obstructed by HVAC plant, exhaust vents, and rooftop car-wash facilities leased to a third party. After obstacle mapping and shading analysis using PVSYST 7.4, 2,100 m² of usable panel footprint was identified in the north and east sections of the retail roof.
Combined usable area: approximately 5,300 m² — sufficient for the 480 kWp system recommended after the load profile analysis.
The energy audit produced a 12-month hourly consumption profile from the facility's BMS (Building Management System) data export. Key findings:
The gap between the compressor-restart MD peak (880 kW average) and the typical trading-day MD (700 kW) was costing the hypermarket approximately RM 5,460 per month in avoidable MD charges — RM 65,520 per year — for a one-hour weekly event.
PV Array: 835 × Trina Vertex S+ 575W
835 units of Trina Solar Vertex S+ 575W monocrystalline bifacial panels were distributed across both roof zones: 520 panels on the warehouse roof (Zone 1) and 315 panels on the usable retail roof sections (Zone 2). The Vertex S+ 575W was selected for its bifacial factor of 0.70 and its Class A fire rating — relevant for rooftop installation above an occupied retail space.
Three Huawei SUN2000-100KTL-M2 string inverters (100 kW each, yielding 300 kW combined AC output from the primary generation zone) were installed in a rooftop plant room on the warehouse roof, with a fourth SUN2000-60KTL-M0 (60 kW) on the retail roof section, bringing total inverter capacity to 360 kW AC against 480 kWp DC — a DC:AC ratio of 1.33, optimised for the KL irradiance profile where clipping losses are minimal.
SmartGuard Backup Module
A Huawei SmartGuard module was integrated into the inverter string configuration to provide uninterruptible supply to a designated critical-load circuit covering the facility's alarm system, CCTV infrastructure, fire safety panel, and cold-chain temperature monitoring equipment. In the event of a TNB grid disturbance (which the energy manager had experienced twice in the preceding 24 months), these loads remain powered from battery-backed solar generation rather than transferring to the diesel generator immediately — reducing generator start events and their associated fuel and maintenance costs.
FusionSolar Load-Shifting for MD Reduction
The FusionSolar SmartLogger 3000A — installed at the main distribution board — monitors real-time facility demand and integrates with the hypermarket's BMS via Modbus TCP. The load-shift configuration implements two specific demand management strategies:
The hypermarket chain is a member of the Roundtable on Sustainable Palm Oil (RSPO) supply chain programme. As a retailer selling RSPO-certified cooking oil, palm shortening, and related products, it is required to demonstrate supply chain traceability and, from 2026, to provide verified Scope 2 emissions data as part of the enhanced RSPO Retail Member requirements.
Previously, compiling this data required manual extraction from TNB bills and conversion using the Suruhanjaya Tenaga grid emission factor — a process the energy manager estimated consumed 15 hours per annual reporting cycle, with a margin of error that had triggered a query from the RSPO auditor in 2024.
FusionSolar's monthly generation report exports directly as a structured CSV with cumulative generation (kWh), avoided CO₂ (tCO₂, using the configurable grid emission factor), and Renewable Energy Certificate-equivalent figures. The energy manager used this export to complete the 2026 RSPO Retail Member annual questionnaire's Scope 2 section in 52 minutes — down from three weeks.
The installation was completed over nine weeks (November 2025 – January 2026), structured around the hypermarket's operational calendar. Key coordination requirements:
Pre-commissioning power quality testing confirmed that inverter operation did not introduce harmonic distortion above the limits of IEC 61000-3-12, a requirement specified by the facility's electrical consultant given the sensitivity of refrigeration control electronics to grid harmonics.
Energy generation:
Average monthly generation: 56,400 kWh — a specific yield of 1,175 kWh/kWp/year, consistent with the P50 design estimate of 1,160 kWh/kWp for the Klang Valley irradiance zone and the system's 1.33 DC:AC ratio.
Monthly bill savings:
Average monthly TNB bill reduction over four months: RM 38,200.
Projected annual savings: RM 458,400. System installation cost: approximately RM 2.98 million (including SmartGuard, BMS integration, and all civil and electrical works). Simple payback: 6.5 years.
Maximum Demand reduction:
First four months of operation showed MD registration reduced from an average of 877 kW (January–December 2025 average) to an average of 598 kW — a 32% reduction. The single largest month-on-month improvement was March 2026, when the compressor restart sequencing protocol operated for the first full month without manual overrides, registering an MD of 572 kW versus the March 2025 figure of 891 kW.
Environmental performance:
The system displaces approximately 660 tonnes of CO₂ equivalent per year, calculated using Malaysia's 2024 grid emission factor of 0.694 kg CO₂/kWh. This figure is now cited in the chain's 2026 annual sustainability report as a verified Scope 2 reduction measure.
Supply chain ESG compliance:
The FusionSolar generation reports have been accepted by the RSPO auditor as verified Scope 2 mitigation evidence for the 2026 Retail Member annual questionnaire. Three supplier audit requests from multinational FMCG brands (received Q1 2026) were answered using FusionSolar data exports, each turnaround completed in under two business days versus the previous three-week cycle.
It is worth isolating the Maximum Demand reduction component because it is the most replicable finding for other hypermarket operators. The 280 kW MD reduction saves RM 14,000 per month — RM 168,000 per year. This saving is achieved primarily through:
The incremental cost of the BMS integration work within the overall project was approximately RM 85,000. The annual MD-reduction saving alone produces a 1.97-year payback on that component — entirely independent of energy consumption savings and the broader PV economics. For any C2-tariff commercial operator with a significant refrigeration load and a compressor-dominated MD peak, the BMS integration logic is the highest-ROI single line item in the project.
Note: Financial figures represent indicative modelling based on Trexon installation data and TNB C2 tariff schedules. Specific client details are anonymised per B2B confidentiality.
Get a free consultation and see how much you can save with solar.