How a five-storey Putrajaya ministry office retrofitted Huawei SUN2000 + Trina Vertex S+ to meet the government's Green Procurement Directive 2026 and achieve 70% administrative load offset
tCO₂ offset annually
“The Green Procurement Directive required our ministry to demonstrate a measurable renewable energy commitment by Q1 2026. Trexon's team understood the JKR tendering process and the MyHIJAU registration requirements inside-out. The system was commissioned on time despite the Putrajaya precinct's additional coordination layers, and MGTC has since listed our ministry as a MyHIJAU showcase reference for other federal agencies. The FusionSolar dashboard gives our procurement team the data they need for Bursa ESG and government sustainability reporting in minutes rather than weeks.”
Malaysia's Green Procurement Directive, introduced in 2025 and effective from 1 January 2026, requires federal government agencies to demonstrate measurable renewable energy adoption as a component of their annual performance KPI frameworks. For facilities management departments across Putrajaya, this created an urgent imperative: identify a credible, auditable renewable energy commitment that could be documented for the MyHIJAU certification programme — Malaysia's official government green procurement label managed by the Malaysian Green Technology and Climate Change Corporation (MGTC).
The ministry in this case study — a five-storey headquarters building in Putrajaya's core administrative precinct — had been on the MGTC MyHIJAU radar since 2024. The building's facilities management team had submitted an initial expression of interest for solar in 2024 under the pre-ATAP NEM 2.0 framework, but budget cycle constraints and the complexity of coordinating with the Putrajaya Corporation (Perbadanan Putrajaya) for precinct design approval had stalled the project. The Green Procurement Directive's Q1 2026 reporting deadline created the necessary urgency to proceed.
The ministry building presents a typical Malaysian government office load profile: significant daytime occupancy (approximately 800 staff across five floors), heavy air-conditioning load (central chilled-water system serving the building), continuous IT infrastructure (server room, network equipment, CCTV), and a covered basement carpark.
Energy audit findings (conducted by Trexon's team in August 2025):
The 280 kWp system is divided across two zones:
Zone 1 — Rooftop Array (210 kWp, 365 panels): 365 units of Trina Solar Vertex S+ 575W panels were installed on the main rooftop using low-profile ballasted aluminium racking. The south-facing main roof section (orientated 15 degrees west of true south, consistent with Putrajaya's urban grid) hosts 290 panels; the remaining 75 panels occupy the east-facing wing roof, which generates meaningfully in the morning hours and improves the system's generation curve alignment with the office's early-morning occupancy ramp.
Two Huawei SUN2000-100KTL-M2 inverters (100 kW each) handle the rooftop array's DC output, installed in a dedicated inverter plant room on the third floor mechanical level — chosen for its proximity to the building's main electrical room and its ventilation provision.
Zone 2 — Carpark Solar Canopy (70 kWp, 122 panels): 122 Trina Vertex S+ 575W panels were installed on a purpose-designed solar canopy structure built over the existing carpark driveway and visitor parking bays. The canopy serves a dual function: generating 70 kWp of PV electricity and providing shade cover for approximately 45 visitor parking bays — a practical benefit noted specifically by the ministry's protocol team, who manage high-level visitor parking during ministerial events.
One Huawei SUN2000-60KTL-M0 inverter (60 kW) handles the carpark array. The canopy structure was designed by a Putrajaya Corporation-approved structural engineer and fabricated from hot-dip galvanised steel, with a 30-year structural design life — aligning with the Vertex S+ panels' 30-year linear performance warranty.
NEM 3.0 / ATAP Grid Connection: The system was filed under ATAP GP/ST/No.60/2025 NEM 3.0 as a commercial-industrial grid-tied system. The ministry's procurement team worked with Trexon to structure the ATAP application to align with TNB's Connection Agreement requirements for government buildings — which have a distinct ownership and billing structure compared to private-sector applicants. Grid-energisation was achieved in February 2026, within five months of contract signing.
Solar installations in Putrajaya's administrative core require coordination with Perbadanan Putrajaya's design review committee — an additional approval step that has historically added 3–4 months to projects attempted by contractors unfamiliar with the precinct's process. Trexon had completed one previous Putrajaya installation in 2025 and maintained a working relationship with the Perbadanan Putrajaya Infrastructure Division.
The carpark canopy design was the primary coordination focus: the committee required the canopy height, column spacing, and visual treatment to conform to the precinct's architectural guidelines. Trexon's appointed architect submitted a design that matched the canopy's steel profile and powder-coat colour to the ministry building's existing external metalwork — a detail that earned a formal "design compliant" designation from the committee in the first review round, avoiding the revision cycles that had cost other contractors months.
MGTC's MyHIJAU programme awards a green procurement label to government agencies that can demonstrate verified renewable energy adoption meeting defined capacity and monitoring thresholds. Trexon prepared the MyHIJAU technical submission package on behalf of the ministry, including:
MGTC awarded the ministry's solar system MyHIJAU Vendor Showcase status — a designation that allows the ministry to be cited as a reference case in MGTC's outreach to other federal agencies. The ministry's Director of Facilities Management was invited to present at MGTC's Green Government Buildings Forum in April 2026.
Generation: Average monthly generation: 32,800 kWh — a specific yield of 1,403 kWh/kWp/year, above the P50 design estimate of 1,380 kWh/kWp for Putrajaya's irradiance zone. The above-estimate performance reflects Putrajaya's lower ambient aerosol levels compared to the Klang Valley industrial corridor, resulting in higher effective irradiance.
Savings: Average monthly TNB bill reduction: RM 9,150, comprising: - Energy consumption savings: RM 8,800/month (32,800 kWh × RM 0.268/kWh blended C1 tariff rate) - Maximum Demand reduction: RM 350/month (marginal, as the 280 kWp system does not materially reduce peak demand relative to the building's 400 kW+ MD baseline)
Projected annual savings: RM 109,800 (rounded to RM 110,000 for planning purposes). System installed cost: RM 793,000 (rooftop + carport). Simple payback: 7.2 years.
Administrative load offset: The system provides approximately 40% of the building's weekday daytime consumption from solar — but since the ministry operates predominantly Monday–Friday daytime, solar covers approximately 70% of the "administrative load" (working-hours consumption excluding server rooms and security base load). This 70% figure is the one cited in the ministry's MyHIJAU submission and Green Procurement Directive KPI report.
Despite representing a large share of Malaysia's commercial building energy consumption, federal and state government buildings have historically been slow solar adopters. The barriers are structural: multi-year capital budget cycles, complex ownership and facilities management structures (many federal buildings are managed by Jabatan Kerja Raya or Perbadanan Putrajaya rather than the occupying ministry), and procurement rules that favour the lowest-bid contractor rather than the most technically capable one.
The Green Procurement Directive 2026 changes this calculus. By making renewable energy adoption a reportable KPI for ministry facilities management departments, the directive creates an internal champion — the Facilities Director — who now has both a mandate and a performance incentive to procure solar, rather than merely an option. Trexon's experience with the Putrajaya approvals process, JKR procurement documentation requirements, and MGTC's MyHIJAU technical submission format positions it as one of very few contractors with a repeatable track record across this application type.
Note: Financial figures represent indicative modelling based on Trexon installation data and TNB C1 tariff schedules. Client details are anonymised per government procurement protocols.
Get a free consultation and see how much you can save with solar.